South Court Street Update
May 13, 2022
Resurface from South Blvd. to Fairview Ave.
Expect Detours and Travel delays between Delano and Fairview most weekdays until May 2022. Thank You for Driving Safely in Work Zones!
Current Phase:
Placing final layer of asphalt, striping and signal head replacement.
Overall Project Completion:
97% and on target for a June 2022 Substantial Completion
South Court Street Update
Oct. 5, 2021
Resurface from South Blvd. to Fairview Ave.
Expect Detours and Travel delays between Delano and Fairview most weekdays until May 2022. Thank You for Driving Safely in Work Zones!
Current Phase:
Replacing storm pipes, replacing sidewalks, gutter lines and base stabilization between Delano and Fairview.
Overall Project Completion:
75% and on target for a May 2022 Completion
Resurface from South Blvd. to Fairview Ave.
Expect Detours and Travel delays between Delano and Edgemont most weekdays until February 2021 Thank You for Driving Safely in Work Zones!
Current Phase:
Replacing Storm Pipes between Delano and Edgemont
Replacing Water Mains between Delano and Fairview
Overall Project Completion:
40% and on target for a September 2021 Completion