Hunter Loop Road Update

Oct. 5, 2021

Resurface and add safety shoulder from Old Selma Road to Birmingham Highway

Current Phase:
Leveling surface applied, drainage structures being installed and traffic signals being delivered.

Project is 70% complete and on schedule for a January 2022 completion.

 
bid.jpg

Resurface and add safety shoulder from Old Selma Road to Birmingham Highway

Current Phase:
Bid Opening scheduled at Alabama Department of Transportation February 26, 2021